
Water and Wastewater
We understand the essence of water and sewage systems in urban development. Our designs champion sustainability, robustness, and efficiency, ensuring communities thrive and environments are preserved.
Completed Projects
PROJECT: HDD OF 20” HDPE FM AT MIAMI INTERNATIONAL AIRPORT
SCOPE OF WORK
The 20” HDD FM for the Miami Internatonal Airport (MIA) serves as the marquee project in our roster; exhibitng Our Team’s commitment to ensure that all our clients concerns are met. The main transmission line at MIA was a 20” cast iron force main (FM); running along NW 21 Street. The FM was a crucial component of the MDWASD Wastewater Transmission system, as it received the majority of the flows from the MIA sanitary sewer collecton system. Due to various factors, the most important of which was age, the force main failed, causing sewage overflows in and around MIA. The nature of the project required an emergency response with an expedited schedule. It was decided by MDWASD and MIA that a trenchless opton would be used to install the new force main; thereby mitgatng the risk of complicatons and prolonged down‐tme. The scope of services for this project included the design and constructon of 800 LF of 20” HDPE force main by horizontal directonal drilling (HDD). The purpose of the project was to replace a failed secon of an existng force main, servicing the Miami Internatonal Airport (MIA). The project was vastly complex, requiring extensive coordinaon to ensure proper alignment, radius of curvature, and entrance/exist angles that would allow the minimum clearance between existng utli‐tes. Additonal coordinaon was required to facilitate a clear path for the directonal drilling below Ramps K, I, and L that service the MiamiIntermodal Center (MIC). The project required constant communication with the contractor, as the team worked around the clock to deliver the project within the ght schedule. The project’s expeditedschedule was met; both in the design and constructon phase. A wellexecuted design and close coordinaton with the emergency opera‐ton contractor allowed constructon to take place within a week’s tme, with no major setbacks. The design was started on January 25, 2010 and completed in a week. By February 15th, 2010 the new line was already in service. Arnelio Alfonso, P.E. (APCTE) was the project manager of the project; overseeing all facets of design and construction.
CLIENT
Miami International Airport / NW 21st Street, Miami-Dade County, Florida
LOCATION
Florida


PROJECT: 11TH STREET, CITY OF MIAMI BEACH, FLORIDA
SCOPE OF WORK
The project entailed the improvements to the Flamingo Park Neighborhood - 11th Street Right-of Way Improvement Project from East of Alton Road to West of Jefferson Avenue and from East of Euclid Avenue to West of Washington Avenue.
The work includes, but is not limited to:
• Reconstruction and improvements to the roadway and streetscapeincluding sitework preparation and earth-work, consisting of the removal of encroachments and the complete reconstruction of the roadway cross section including a design profile and cross slope by raising the roadbed to a minimum road crown elevation of 3.7 NAVD.
• Construction of enhanced bulb-outs, new landscaping, and a new irrigation system at each intersection which will be like those prepared on the on-going 11th Street (Jefferson Avenue to Euclid Avenue) Project Installation of a new stormwater system consisting of the removal of the existing drainage system as well as designing and constructing of a new 36-inch Concrete Reinforced Pipe, P-5’s and P-6’s drainage structures, and the connection to an existing outfall• Installation of drainage system in private properties, such as yard drains and/or driveway trench drains, to maintain positive drainage away from the private lots.• Improvements of the water main which will consist of removing the existing water mains (WM) and fire hydrants (FH) and installing a new 8-inch WM with minimum 2-inch services; this will include new water meters with automated meter reading technology.• Improvements of the Gravity Sanitary Sewer (SS) will consist of removing the existing SS mains and installing a new 18-inch and 24-inch PVC SS Mains and manholes. Also, responsible for the office administration construction progress activities related to the construction of this right-of-way improvement project. Some of the construction management services provided for this project included:• Weekly construction meeting/coordination• Review shop drawing• Respond to request for information (RFI’s)• Evaluate Request for changes to project schedules• Contract documents control
CLIENT
CITY OF MIAMI BEACH
LOCATION
Miami Beach, Florida

PROJECT: NW 7TH AVENUE WASTEWATER COLLECTION SYSTEM EXPANSION: SUB-BASIN D2-D2 GRAVITY SEWER AND FORCE MAIN
SCOPE OF WORK
E Plus was part of the design of this important project and formed an inspection team that is in charge during construction ensuring that everything was executed under the specifications required for it. This project consists of the expansion of the Wastewater Collection System, which is being installed along the NW 7th Ave and adjacent streets from NW 136th St to S Biscayne Riv Dr. The System is divided into two sub-basins: D2-D2 comprising from NW 143rd St to S Biscayne Riv Dr, and the
Sub-Basin D2-D3 from NW 135th St to NW 144th St. Additionally, the facility is under two operating systems: Gravity Sewer and Force Main, and involves the following:
• Installation of 3,036 L.F. of 8-inch Ductile Iron (D.I.) force main, valves, and fittings
and 10,082 L.F. of 8-inch PVC pipes and fittings in Sub-Basin D2- D2.
• Installation of approximately 2,928 LF of 8-inch Ductile Iron (D.I.) force main, valves and fittings, 1,188 LF of 8-inch Ductile Iron (D.I.) Sanitary Sewer pipes and fittings, and 6,451 LF of 8-inch PVC pipes and fittings in Sub-Basin D2-D3
CLIENT
M-D WASD
LOCATION
NW 7th Avenue
Furnishing and installing the 8-inch ductile iron pipes with restrained joints where required; valves, and automatic air release valve assemblies. Work includes, as well, cleaning and testing the proposed force mains and gravity sewer lines.
• Permanent pavement restoration; full width milling and asphalt overlay of existing roadways; and, replacing pavement markings.
• Ancillary work includes all permitting; dewatering; storm water pollution prevention; removing unsuitable soils and installing suitable backfill material where required.
• Replacement of sod and shrubs, tree protection, trimming, root pruning, and dewatering the force mains after shutdown.
Additional project activities involve Mobilization and design submittals; site restoration of sidewalk, curb andgutter; cleanup after activities; maintenance of traffic during construction and public involvement.


PROJECT: PERRINE CUTLER RIDGE WATER & SEWER IMPROVEMENTS
SCOPE OF WORK
The scope of work was comprised of an upgrade to the existng water and sewer system in the area to beter meet the aggregate demand of several large scale future developments. The existng system was undersized and, in many cases, did not service a significant porton of the area. These condi‐tons inhibited commercial and residental development. MDWASD aspart of the water & sewer improvements for Perrine‐Cutler Ridge, proposed the installation of 12” and 16” watermains, new fire hydrants, and the expansion of the gravity sewer system in order to route flows to the new public sta‐tons. The project was divided into three Basins and it served an area of approximately 181 acres.
Overall the project included approximately 20,000 LF of water main, 23,000 LF of sanitary sewer, 8,000 LF of force main, and 3 pump statons; with a constructon cost totaling $17.8 million. MDWASD completed the project in a cost and tme effectve manner; overhauling the water and sewer system in the area, and providing public water and sewer services to many propertes.
CLIENT
M-D WASD
LOCATION
Perrine Cutler Ridge Area , Miami-Dade County, Florida
The existng system was comprised of undersized water mains, old water mains, and in some cases no water mains in the project area. The land use is com‐mercial, industrial and residenal; and mostly served by undersized water mains or private wells. Addionally, a vast majority of the area was serviced by sepc tanks, private li staons, and in a few cases public sanitary sewer systems.
The water distributon scope of work was comprised of approximately
18,000 LF of 12” WM and various other water mains ranging in diameter from 6”‐16”. The upgrades will also provide fire protecton and improved pressures to the neighboring commercial, industrial and residen al propertes in the project area.
The new sanitary sewer system included: various 8” D.I. gravity mains. There is approximately 18,000 LF of 8” sanitary sewer and about 5,000 LF of 12” sanitary sewer. These gravity lines routed flows to the new pump statons. Flows were then transmited via a new 12” DIP force main to a 54” Transmission Main. These improvements eliminated the need to maintain the smaller public and private li statons in the area, which in turn is a savings to the owner. Arnelio Alfonso, P.E. (APCTE) was the project manager of the project; overseeing all facets of design and constructon.


PROJECT: 54”DI WATER MAIN ALONG NW 57TH AVE (W 4TH AVE)
SCOPE OF WORK
This project is a prime example of Our Teams experience with Large Diameter Pipelines. The 54 “ ductle iron water main along W 57th Ave. is a first of its kind project in South Florida. The scope of work for this project is comprised of the installaton of 380 LF of 54” DI WM across the Litle River (C‐7) Canal, via a sub‐aqueous crossing.
From concepon, the project was intrinsically complex require extensive coordinaon between all project stakeholders. However, due to a change in the design of the adjacent roadway constructon; an elaborate post‐design effort was required to ensure that MDWASD receives a quality product.
CLIENT
M-D WASD
LOCATION
NW 57th Ave. (W 4th Ave.) & W 53rd St. Intersection, Hialeah, Florida
Our Team worked around the clock coordinating with the contractor, pipe manufacturer, and owner to mitigate the risk of possible construction delays. Ater evaluating the scenario, a specialty contractor was brought on‐board to assist with the sub‐aqueous crossing; thereby turning the project into a hybrid between a design‐build and conventional hard bid project. During the entire process E plus coordinated closely with MDWASD to ensure that their best interests were met at all times. This included contract negotiations with the contractor and implementing innovative solutions to limit manufacturer related production delays. E plus, as the Engineer of Record, provided production plans & specific tons, secured all required permits, and provided construction management services as required. Additional efforts by our team included a buoyancy analysis of the pipe, due to its large diameter, and 3D modeling to provide QA/QC during the pipe’s construction.



PROJECT: MIC WATER & SEWER IMPROVEMENTS PROJECT
SCOPE OF WORK
.The Miami Intermodal Center (MIC) Water and Sewer Improvement Project provided upgrades to meet the needs of the MIC area and the new rental car facility (RCF). As the Engineer of Record (EOR),
E plus designed a complete overhaul to the areas water & sewer system. The Project consisted of the design of a new regional lift station (PS 101), a gravity sewer system, a 12” force main, and a 24” water main.
The water main scope of work consisted of 2500 LF of 24” DI WM along NW 21st St. and along NW 38th Ct. Addionally, 2100 LF of 16” WM was installed along SR 953 / LeJeune from NW 25th St. to NW 30th St. The project included a crossing of the CSX Railroad right‐of‐way with a 30” casing.
CLIENT
M-D WASD
LOCATION
Miami Intermodal Center, Miami-Dade County, Florida
The sanitary sewer scope of work for the project included the installation of a new regional station (PS 101, 1050 GPM), construction of 1,580 LF of 12” DIP gravity sewer system, and installation of 1,400 LF of 12” force main. This project required extensive coordination with governmental agencies to obtain all necessary permits (i.e. FDOT, M‐D County, DRER, Building Department, and MDWASD approval).

